- 2016
- File Notice of Intent (NOI) and Pre-Application Document (PAD) (5 ½ yrs before expiration)
- FERC scoping
- 2017
- Develop Study Plans in coordination with stakeholders
- File Proposed Study Plan (PSP) – Deadline to file PSP – 1/13/2017
- File Revised Study Plan (RSP) – Deadline to file RSP – 5/15/2017
- Conduct studies
- 2018
- Complete remaining study efforts
- File initial study reports
- Consultation with stakeholders
- 2019
- File updated study reports
- Consultation with stakeholders
- Develop environmental protection, mitigation, and enhancement measures
- File Preliminary License Proposal (PLP) or Draft License Application (DLA) - Deadline to file DLA – 9/3/2019
- Prepare Draft Biological Assessments
- Prepare Final License Application (FLA) - Deadline to file FLA 1/31/2020
- 2020-2022
- National Environmental Policy Act (NEPA) document
- Prepare Initial Study / Mitigated Negative Declaration document
- File 401 Certification application
- License Expires 1/31/2022